Border to Border trail continues to move along

Courtesy photo. Workers have poured the first 100 foot of curb and gutter along Dexter-Chelsea Road near the railroad.

(Chelsea Update would like to thank Roy Townsend for the information and photos in this story.)

The Board to Border Trail updates are as follows:

The contractor has completed the path grading and placement of the stone base for the path and the combined driveways.

Workers have poured the first 100 foot of curb and gutter along Dexter-Chelsea Road, near the railroad.

The 70-foot long bridge over Mill Creek was set into place and the concrete bridge deck will be poured later this month.

Also later this month, the contractor plans start paving the 10-foot wide path.

The slope restoration will then follow the paving, in late June or early July.

Courtesy photo. The 70-foot long bridge over Mill Creek was set into place.