Here’s the latest update on the M-52 construction

Here’s the latest on the M-52 construction project from the Michigan Department of Transportation.

file photo

From 5 a.m.- 7 p.m., miscellaneous work continues for water main installation and driveway placement prep.  All three lanes on M-52 are open to traffic: one southbound lane, one northbound lane and a designated left turn lane.

From 7 p.m.-5 a.m., traffic is reduced to one lane in each direction along the west side of M-52 and the contractor will be working along the east side of M-52 completing driveways and sidewalks.

On Monday, Oct. 15, at 5 am, until about 8 p.m. on Tuesday, Oct. 16, M-52, north of I-94, will be reduced to one lane in each direction for milling and paving.

On Wednesday, Oct. 17, from 7 p.m. to 5 am, there will be a detour for southbound M-52 traffic between I-94 and Old US-12 for paving in the southbound and left turn lane on M-52.

On Friday, Oct. 19, between 7 p.m. – 5 a.m., the contractor will close and detour the westbound I-94 off-ramp to M-52 for paving on the ramp.

On Monday, Oct. 22, between 7 p.m. – 5 a.m., the contractor will close and detour the westbound I-94 on-ramp from M-52 for paving on the ramp.

Please note that all closure or detour dates are tentative, and weather dependent, so any interruptions due to the weather will most likely shift the entire schedule.