Latest update on the Border to Border Trail

Courtesy photo. Progress being made on the Border to Border Trail.

(Chelsea Update would like to thank Roy Townsend for the information and photos in this story.)

The contractor has completed approximately 90 percent of the path grading and placement of the stone base for the path and the combined driveways.

The contractor has also poured and backfilled the two bridge abutments.

The Chelsea Ridge HOA has agreed to have the contractor connect the path to their subdivision with a 5-foot wide sidewalk, which will be done later this month or in early June.

Later this month, the contractor plans to set the bridge and in early June the company plans to start paving the 10-foot wide path.

The slope restoration will then follow the paving, in late June or early July

Also, five concrete pyramid foundations that were dug up east of Fletcher Road were determined to be part of the railroad water tower foundation from decades ago, and we plan to place them in the same area we dug them up, so that trail users will be able to enjoy them.

Courtesy photo. Crews work on the Border to Border trail.

 

Print Friendly, PDF & Email

More News

In Photo by Randall Lee: Ballet Chelsea Holds Chelsea Chamber of Commerce After Hours Event

April 8, 2024

Chelsea Track and Field Scrimmage at Brighton High School (with Slideshow)

April 8, 2024

Attorney General Offers Tips Following ATT Data Breach

April 8, 2024

April 9: What’s on the Lyndon Township Board Agenda

April 8, 2024

April 8: What’s on the Chelsea Board of Education Work Session Agenda

April 8, 2024

‘The Antichrist Cometh’ is Action-Packed Entertainment at Purple Rose Theatre

April 7, 2024

April 13: Chelsea Area Garden Club Fundraiser at Chelsea Expo

April 7, 2024

April 14: Messy Church at Chelsea First UMC

April 7, 2024

Chelsea 2024 Marriage Summit at Main Street Church

April 7, 2024

No City of Chelsea Meetings This Week

April 7, 2024

Chelsea Kiwanis Club Hears about SRSLY

April 6, 2024

April 13: Spring Break Craft/Vendor Show at Chelsea Fairgrounds

April 6, 2024

April 8: Daytime Road Closure on Waterloo Road

April 6, 2024

Reminder: Collage Concert April 6 at Chelsea High School

April 6, 2024

Department of Veterans Affairs Enrolls More Than 7,000 Michigan Veterans

April 6, 2024

This Week’s Washtenaw County Road Commission Projects

April 6, 2024

April 13-14: Chelsea High School Theatre Guild Presents ‘The House of Atreus’

April 5, 2024

April 12-13: Foam Recycling behind Stivers Restaurant

April 5, 2024

Let’s Get Gardening in April, Part 2

April 5, 2024

Check Out These City Board and Commission Openings

April 5, 2024

State AG Reissues Information about Debt Relief Scams

April 5, 2024