Beginning Monday, June 27, Werkner Road in Sylvan Township will be closed at M-52 as the work begins on the roundabout at the corner of M-52 and Werkner Road.
Temporary traffic signals are being installed to maintain two-way traffic on a single open lane throughout construction.
Stage 1 is scheduled to begin on Wednesday, June 29 and the roundabout is scheduled to be complete and open to traffic by Aug. 25.
A preconstruction meeting was held on June 21 and the prime contractor is D and R Earthmoving, LLC, while Wade Trim will be administering the construction contract for the MDOT Brighton TSC.